Case: Fingrid PLC

July 2011 - April 2013


In spring 2011 Porin Teollisuusputki was chosen to execute the fuel piping system of a new 200MW reserve power plant in Forssa as an EPC contract, including among other things the designing of the piping and pipe supports and the procurement of the equipment.

After the contract itself was complete, PTP was also involved in the commissioning. The client also commissioned an additional project in which the system's safety was further developed to correspond to the wishes of Fingrid PLC.